S
Saviz
Hi Guys,
I have Several resource a,b,c,d..etc. And list of hours for each resource
depending on task they work on.
Is there a way to paste several units (in taskinformation -> units field )?
Example:
Task Design have following resources assign to it:
Design-Resource a
Design-Resource b
Design-Resource c
Design-Resource d
Each resource have specific units in hrs for design task.
Design-Resource a - 2hr
Design-Resource b -4 hr
Design-Resource c -5hr
Design-Resource d -6hr
...
I want to be able to simply paste my units rather than adding them one by one.
Thanks.
I have Several resource a,b,c,d..etc. And list of hours for each resource
depending on task they work on.
Is there a way to paste several units (in taskinformation -> units field )?
Example:
Task Design have following resources assign to it:
Design-Resource a
Design-Resource b
Design-Resource c
Design-Resource d
Each resource have specific units in hrs for design task.
Design-Resource a - 2hr
Design-Resource b -4 hr
Design-Resource c -5hr
Design-Resource d -6hr
...
I want to be able to simply paste my units rather than adding them one by one.
Thanks.