J
jem
I have two situations in which multiple people want to own/be the PM for a
project.
Situation 1: A team has a large project with the Project Manager delegating
some tasks to a lead on his team. At times, the PM makes changes to the
schedule and republishes task assignments. Another day, his lead may make
changes and republish task assignments. These two people want to receive
PWA updates for the tasks they have changes/republished.
1) Does this republish not make the last person publishing the project
the owner/PM for all tasks?
2) Will the last person publishing the project be the one to get the
PWA time updates?
3) Is it possible to assign PM ownership at the task level rather than
project level? If so, if both
people happen to change the same task and time is posted between
the two updates, how would
project know which to post. For example: PM 1 changes Task A and
republishes on Monday, and the resource posts 2 hours of time to it
and updates so PM 1 gets the email notification. PM 2 changes Task
A on Tuesday and republishes that day. The resource posts 3 hours time for
that day and the PWA update goes to PM2. On Wed, both PM 1 and PM 2
try to update the
project. Will both the 2 hours and 3 hours post? Or only one of
these?
Situation 2: Similar to the first one. One project wants to have multiple
people changing/managing tasks within a project schedule. They want to
break the tasks up across several people and have each person make their
changes, republish, and get the PWA email update notifications, then each
will post the actual hours to their respective set of tasks.
Are these situations possible? I thought a project could have only one
owner/PM at a time? Thanks for any assistance.
jem
project.
Situation 1: A team has a large project with the Project Manager delegating
some tasks to a lead on his team. At times, the PM makes changes to the
schedule and republishes task assignments. Another day, his lead may make
changes and republish task assignments. These two people want to receive
PWA updates for the tasks they have changes/republished.
1) Does this republish not make the last person publishing the project
the owner/PM for all tasks?
2) Will the last person publishing the project be the one to get the
PWA time updates?
3) Is it possible to assign PM ownership at the task level rather than
project level? If so, if both
people happen to change the same task and time is posted between
the two updates, how would
project know which to post. For example: PM 1 changes Task A and
republishes on Monday, and the resource posts 2 hours of time to it
and updates so PM 1 gets the email notification. PM 2 changes Task
A on Tuesday and republishes that day. The resource posts 3 hours time for
that day and the PWA update goes to PM2. On Wed, both PM 1 and PM 2
try to update the
project. Will both the 2 hours and 3 hours post? Or only one of
these?
Situation 2: Similar to the first one. One project wants to have multiple
people changing/managing tasks within a project schedule. They want to
break the tasks up across several people and have each person make their
changes, republish, and get the PWA email update notifications, then each
will post the actual hours to their respective set of tasks.
Are these situations possible? I thought a project could have only one
owner/PM at a time? Thanks for any assistance.
jem