J
Jazzman201
We have a corporate resource pool, and people are assigned to many projects
at once. At present, we have projects retained on the server back to 2005.
Here's my problem: I have a resource who has 7 project assignments back to
2005. All projects are completed, but some show Remaining Work. These 7
projects show 5 different amounts of Remaining Work for this resource, and of
the 5, only 1 is correct. The total of Remaining Work is around 3,500 hours.
It should be closer to 2,000 hours.
I can not simply correct Remaining Work for each project and re-publish the
full plans, because many resources on these projects have left the
organization: our policy is to delete the Winders User Account immediately
when they leave, so I get spooler errors for missing accounts and the changes
have to be backed out.
Even if I open all plans at once, and re-publish New and Changed Assignments
for each, I can't get the Remaining Work numbers to agree. Anyone have any
ideas as to how to fix this??
at once. At present, we have projects retained on the server back to 2005.
Here's my problem: I have a resource who has 7 project assignments back to
2005. All projects are completed, but some show Remaining Work. These 7
projects show 5 different amounts of Remaining Work for this resource, and of
the 5, only 1 is correct. The total of Remaining Work is around 3,500 hours.
It should be closer to 2,000 hours.
I can not simply correct Remaining Work for each project and re-publish the
full plans, because many resources on these projects have left the
organization: our policy is to delete the Winders User Account immediately
when they leave, so I get spooler errors for missing accounts and the changes
have to be backed out.
Even if I open all plans at once, and re-publish New and Changed Assignments
for each, I can't get the Remaining Work numbers to agree. Anyone have any
ideas as to how to fix this??