Francis
I have a task 1 with 2 resources A & B.
A is available all the time for working on the task for 10 days
B is availble from Dec 1 onwards for working on the task for 10 days
Project plans the task from Nov 2 onwards.
The task schedules shows that resource A works from Nov2 to Nov 15,
resource B from Dec1 to Dec14
Task 2 depends FS on task 1, both resources (A & B).
In real life Resource A can continue to work on Task2, while resource B is
finalizing Task 1.
How should the tasks be structured so that project can plan correctly.
Francis
A is available all the time for working on the task for 10 days
B is availble from Dec 1 onwards for working on the task for 10 days
Project plans the task from Nov 2 onwards.
The task schedules shows that resource A works from Nov2 to Nov 15,
resource B from Dec1 to Dec14
Task 2 depends FS on task 1, both resources (A & B).
In real life Resource A can continue to work on Task2, while resource B is
finalizing Task 1.
How should the tasks be structured so that project can plan correctly.
Francis