E
eugene76
Hello,
I have an MPD file containing approximately 30 projects which I intend to
resource level regularly in order to achieve two outcomes;
a) manage assigned peoples time across multiple projects
b) schedule a machine's use across multiple projects
I am unsure which is the best course to take with the combination of
Resource pools and calenders to achieve this.
I would like to know how MS Project manages levelling resources (i.e. how it
will split the times after levelling, etc..) under the following
circumstances;
1) one resource pool & two calenders (i.e. normal default calender [1] all
people resources & 24 hours calender [2] for machines)
2) two resource pools (i.e. one pool for people resources with [1] calender
& another pool with [2] calender)
Further I would like to know if there are any other considerations/variables
that I should be aware of.
I would be greatful for any advice,
Many thanks,
eugene
I have an MPD file containing approximately 30 projects which I intend to
resource level regularly in order to achieve two outcomes;
a) manage assigned peoples time across multiple projects
b) schedule a machine's use across multiple projects
I am unsure which is the best course to take with the combination of
Resource pools and calenders to achieve this.
I would like to know how MS Project manages levelling resources (i.e. how it
will split the times after levelling, etc..) under the following
circumstances;
1) one resource pool & two calenders (i.e. normal default calender [1] all
people resources & 24 hours calender [2] for machines)
2) two resource pools (i.e. one pool for people resources with [1] calender
& another pool with [2] calender)
Further I would like to know if there are any other considerations/variables
that I should be aware of.
I would be greatful for any advice,
Many thanks,
eugene