Multiple Resource Rates

S

Sally

I am only just starting to use MS Project for costs and
want to add 3 different rates against each resource. As
these are 'blended rates' they are common for all
resources at the same grade.

I managed to enter the standard rate easily by inserting
the column against all reosurces in the resource pool and
dragging the same rate down for all common resources. Is
there an easy way to do this for the 'B' and 'C' rates or
do I have to go into the resource information for each
resource individually and apply the rate?

Many thanks in advance

Sally
 
D

Dale Howard [MVP]

Sally --

If you wish to use Cost Rate Tables B-E for your resources, you will need to
double-click each name individually and enter the alternate rates. This
would be a good situation for a macro to speed up the entry of the alternate
rates, wouldn't it? Hope this helps.
 