J
Jo_Martin
I am using multiple resources as a pool carry out several tasks - with the
intention that whoever is available can be allocated. I've run into problems
as it seems that P2007 needs to use all the resources allocated before it can
schedule the end of a task. If I set up a task as effort driven and allocate,
say 7 resources, Project will allocate resources as they are available - and
if not available, will leave the resource on the task at 0 hours.
It seems that Project is waiting for this resource to be available (for 0
hours) before it can schedule the end of the task.
To illustrate this behaviour, set up a multi task project (I used 12) and
allocate the same resources to all ( say 7), same work for each task (say 56
hours). Note the finish date. Now allocate non working time to one resource
(say a week). The tasks will increase in duration, and the finish date will
move out because of the holiday - fair enough.
Now delete the resource with the holiday. The overall project finish date
gets earlier....
So with less resource availablity, the project duration is shorter!
While that is an interesting exercise, I'd really like an answer to my
problem, which is how to get maximum resource on a task from a pool of
resources, none of whom are critical to completion of the task.
Cheers
Jo
intention that whoever is available can be allocated. I've run into problems
as it seems that P2007 needs to use all the resources allocated before it can
schedule the end of a task. If I set up a task as effort driven and allocate,
say 7 resources, Project will allocate resources as they are available - and
if not available, will leave the resource on the task at 0 hours.
It seems that Project is waiting for this resource to be available (for 0
hours) before it can schedule the end of the task.
To illustrate this behaviour, set up a multi task project (I used 12) and
allocate the same resources to all ( say 7), same work for each task (say 56
hours). Note the finish date. Now allocate non working time to one resource
(say a week). The tasks will increase in duration, and the finish date will
move out because of the holiday - fair enough.
Now delete the resource with the holiday. The overall project finish date
gets earlier....
So with less resource availablity, the project duration is shorter!
While that is an interesting exercise, I'd really like an answer to my
problem, which is how to get maximum resource on a task from a pool of
resources, none of whom are critical to completion of the task.
Cheers
Jo