P
Product Mgr.
I am using MS Project Web Access to collaborate on a project using the
Percentage Complete method. I have assigned several tasks to multiple
(human) resources. As long as one resource tells me the task is complete, I
consider the work done.
If I assign multiple resources to one task, is it necessary for each
resource to send updates for that task? Or, if one resource reports a task
is 100% complete, will this eliminate the need for all resources to report
the task as being complete?
Percentage Complete method. I have assigned several tasks to multiple
(human) resources. As long as one resource tells me the task is complete, I
consider the work done.
If I assign multiple resources to one task, is it necessary for each
resource to send updates for that task? Or, if one resource reports a task
is 100% complete, will this eliminate the need for all resources to report
the task as being complete?