Multiple resources assigned to a task

B

Babar

Hi,
I had a question related to assigning multiple resources to a task.
Here is the scenario:

- Let's say a task is assigned 8 hrs of work
- 4 resources are assigned to it, with each resource 100% units
- Therefore, each resource is supposed to work 2 hrs on this task.
Correct?
- The first 3 resources enter their actual work = 2 hrs and adjust
remaining time to 0 hrs.
- The 4th resource didn't end up working on the task and therefore,
enters actual work = 0hrs and remaining work = 0hrs.

Now my question is will Project show the task as 100% complete or not?
Secondly, would it adjust the original work value? Finally, does the
total actual work end up as 6hrs?

Thanks. I'd appreciate the help.

Babar
 
R

Rod Gill

Hi,

Yes the task should be 100%, yes it does adjust original work and yes the
actual work is 6.

Select Tools, Tracking, Save Baseline before updating to track where you are
after updating compared to before.
 
B

Babar

Thanks Rod for the insight.

Also, what if the 4th resource doesn't enter the time? Would it show
the task 100% complete then even though the 4th resource didn't perform
any work on that particular task?

Babar
 
R

Rod Gill

If the 4th resource still has work, the task can't be 100% complete. But if
they have 0 work and 0 remaining work it can.
 