I am using MSP2003 for planning a hardware upgrade, and have a resource per
server (all on the 24 hour calendar), a resource for the engineers (2
engineers, so available 200%, and a working time calendar)
When I create a task, specifying the server resource 100% and the engineers
100% (so using one engineer), levelling the project places the the resource
usage for the server and the engineer at different times of the day (or even
different days - I wish I could do these in real life!).
What can I do to prevent this happening?
Thanks in advance
I am using MSP2003 for planning a hardware upgrade, and have a resource per
server (all on the 24 hour calendar), a resource for the engineers (2
engineers, so available 200%, and a working time calendar)
When I create a task, specifying the server resource 100% and the engineers
100% (so using one engineer), levelling the project places the the resource
usage for the server and the engineer at different times of the day (or even
different days - I wish I could do these in real life!).
What can I do to prevent this happening?
Thanks in advance