Thanks for the information. My first suggestion is to install
SP-1
for Project 2007.
I don't believe the resource calendars are responsible for
overwriting
the work values that you manually entered. The 40 hours I am
referring to is the *duration* measurement of 5 days. If your
resources have modified calendars that would change *when* work is
scheduled but should not account for the increase in work values
you
specifically entered.
What method are you using to enter resource names and work on the
task?
If you'd care to, feel free to zip the file and send it to me by
email. I'll take a look and see if I can determine what else is
going
on. My email is prjng[at]maine[dot]rr[dot]com -- replace the
[values]
with the equivalent symbols.
Julie
I have Project Standard 2007, no service pack. I think my
specific
resource
calendars may be complicating the issue, but I'm not sure. The
examples you
gave assume a 40-hr week, but only 2 of my resources are working
with the
standard calendar at 40-hrs per week at 100% units. The others
work
very
specific hours and days on a limited (75%) basis. That would
explain why the
last 2 were fine. It still puzzles me why the work hours
increased
for the
first two resoures and why my assignment units vary from yours:
My example:
Manager (36%) = 12.4h
Engineer 1 (40%) = 11.2h
Engineer 2 (38%) = 3h
Quality = (25%) = 2h
Your example:
Manager (5%) = 2 hr
Engineer1 (8%) = 3 hr
Engineer2 (8%) = 3 hr
Quality (5%) = 2 hr
I did re-enter the task in the order you suggested, but received
the
same
results as before.
:
Hello,
Okay, let's start back at the beginning: what release of
Project
are
you using and what service pack?
In both Project 2003 (SP-3) and Project 2007 (SP-1 +
Infrastructure
Update):
When I step through your example below, I do NOT get the
figures
that
you show. When assigning resources to a 5 day fixed-duration
task
I
see the following:
Manager 5% 2 hours work
Engineer1 8% 3 hours work
Engineer2 8% 3 hours work
Quality 5% 2 hours work
The assignment units are calculated by work/duration =
assignment
units
So for the manager & quality 2/40 = 5%
Engineers 3/40 = 7.5 which project rounds to 8%
I believe the difference you are seeing is due to the order in
which
you did things. I created the task and set it as fixed
duration.
Then I assigned the resources. I have upon occasion seen what
you
report when attempting to assign resources and change task type
all
at
one time, creating odd calculations for the first several
resources
and correct calculations for the remaining. In your example
the
first
two resource assignments were completely unexpected but the
second
two
were fine.
I suggest
1. removing all resource assignments
2. ensure you've set the correct task type for what you wish to
calculate
3 assign the resources
I personally use the Task Entry view which is Gantt chart at
the
top
and Task Form at the bottom. The easiest way to display is to
choose
Window > Split from a full screen Gantt chart view.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information
about Microsoft Project
Julie,
Can we look at an example from my project plan? I'm still
not
clear
on how
the formula works (duration * assignment = work).
I have a task that is supposed to have a 5-day duration,
called
"Complete
Validation on Printer." I have 4 people assigned. In the
Resource
Sheet, I
have the first two people with 75% time allocated to the
project,
while the
last two people are allocated at 100% assignment units.
I first entered the task into the plan. I then entered the
resources' time
(work), in the following manner:
Manager = 2h
Engineer 1 = 3h
Engineer 2 = 3h
Quality = 2h
I left the assignment units blank. I fixed the duration at 5
days.
When I
hit enter, the work and assignment units changed in the
following
way:
Manager (36%) = 12.4h
Engineer 1 (40%) = 11.2h
Engineer 2 (38%) = 3h
Quality = (25%) = 2h
How does Project calculate the assignment units in the above
example
(also
what impact do the original assignment units in the Resource
Sheet
have on
this particular task)? Why do the work hours for the Manager
and
Engineer 1
increase? How is the formula "duration * assignment units =
work"
used when
multiple resources are assigned to a task?
:
Hello CSW,
By default when you assign a resource to a task, project
will
calculate the amount of work for each resource based upon
task
duration * assignment units = work. By default, the work is
spread
evenly over the task duration at a "flat" contour using the
assignment
units.
On tasks with multiple resources with varying amounts of
work,
such
as
you describe, Project will still follow the assignment unit.
For
example: if I have a 5 day duration task with the following
three
resources assigned:
Bob 100% 40 hours
Pete 100% 8 hours
Sue 100% 16 hours
Because of the 100% assignment units for both Pete and Sue
combined
with their calendars, each resource is working 8 hours per
day.
Pete
works on the first day of the task and his work is done. He
would
be
able to be assigned to another task starting day 2. Sue
works
day
1
and day 2 and is available to be assigned to another task
starting
day
3.
If you want Pete's 8 hours and Sue's 16 hours to be spread
evenly
over
the 5 day duration, you'll need to tell project that in some
manner.
In order for Project to understand that you wish to spread
the
resource's work out over a longer task duration, set the
task as
a
fixed duration task. Then when you assign Pete, specify 8
hours
work
and Project will calculate a 20% assignment unit. Assign
Sue
with
16
hours of work in a 5-day fixed duration task and Project
will
calculate 40% assignment units.
Look in Project help for a help topic "About task types" and
it
does a
very good job explaining what gets calculated based upon
what
task
type you've set.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information
about Microsoft Project
I have a project with around 300 tasks. For each task I
have
entered
a
duration and specified multiple resources with varying
work
hours
on
each
task. Within the Resource Sheet, I have specified some of
my
resources at
100% units and others at 75%, due to their unavailability
of
being
100%
allocated to project tasks.
I have many resources over-allocated and am attempting to
reassign
some
tasks to additonal resources to reduce the
over-allocation.
While reviewing the tasks in the Task Usage view, I have
noticed
that some
of the resources are spreading their time evenly over the
total
Duration of
the task, while others have their time condensed into one
day.
I
have only
been using Project for a few months and realize I have a
lot
to
learn.
Please tell me if there is a better way to schedule these
tasks
and
resources
so all resources for a particular task will spread their
work
time
evenly
over the entire task duration. Thanks.