multiple resources

M

Maanu

Hi,

I have to use two resources for a task 'estimate preparation'. One resource
will be allocated 50% from 5-Apr to 9-Apr. The second resource will be
allocated 100% from 5-Apr to 16-Apr.

What would be the right technique for handling such a situation?

Thanks!
 
J

Jan De Messemaeker

Hi,

Gantt Chart
Window, Split
In top pane select the task
Make sure the task is NOT fixed duration
In bottom pane assign both resources
First with 2.5 d of work
Second with 10d of work
Now (and only now) click OK

HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
M

Mike Glen

You can't If you must have such links, then break down the task into 2 separate tasks.

Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials


Hi,

It worked. But How can I link the first resource with another task starting
 