Multiple resources

K

Keith

I have a task that takes 40 days. How do I get Project to automatically
change it to 20 days if I assign another resource?

Thanks
 
J

JulieD

Hi Keith

what you're after is the default behaviour of Project :-
if you enter a task with a 40d duration and assign one resource (at 100%)
the duration will (all other things being equal) stay at 40 days, if you ADD
another resource (at 100%), Project will decrease the duration to 20 days.

If this is not happening automatically, check that the task type is Fixed
Units and that Effort Driven is ticked (double click on the task) and that
calculation is set to automatic (tools / options / calculation tab).

cheers
JulieD
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top