multiple selections from custom field in Project Pro 2007?

J

Jesse

On a project schedule I want to indicate who is responsible and who is
accountable for each task (by role)....in a way that's easy for the novice
user to understand. I'm thinking I want to keep this indication separate
from the resource sheet. So it looks like an easy solution is to create a
custom task field of type = text. This works fine as long as each task has
only one role (pm, dev, test, etc) responsible or accountable. It get
challenging if a task has both dev and test responsible. Is there a way to
select multiple values from a custom field?
 
J

JulieS

Hello Jesse,

No, sorry. No field is multi-select in Project except the Resource Name
field. You'd need to create the options (PM, Test, PM & Test) as a selection
in the list.

I hope this helps. Let us know how you get along.

Julie
 