Multiple Shift Schedules

L

Learning Project

Does Microsoft Project 2002 support multiple shift schedules?

If not does Microsoft Project 2003?
 
S

Steve House [MVP]

They both do if you mean what I think you mean. You can have multiple base
calendars in both versions. For a 24 hour operation you might have one base
calendar for the day shift work hours, another for the swing shift, and a
3rd for graveyard. When you create your resource list you designate the
base calendar for that resource that corresponds to their shift assignment.
When you assign the resource to a task, the schedule for that task will
correspond to the hours of work of the resource assigned to it.
 