Hello i am using MS Project Professional 2007 and Project Server 2007.
Please, is there a way that i can specify multiple hourly rate for a resource.

Thank you
 
D

Dale Howard [MVP]

ghostme --

Assuming you are the Project Server administrator, open the Enterprise
Resource Pool and check out the relevant resources. Double-click the name
of the first resource and click the Costs tab. On the Costs page you will
see five tabs, labeled A (Default), B, C, D, and E. You can enter alternate
rates on Cost Rate Tables B-E. Hope this helps.
 