V
vb6dev2003
Hi,
I have what may seem a stupid question (new to Project):
I have a project with a lot of concurrent tasks. I have 1 single resource
only. I would like to assign that resource on each task, and I would like
the time to be spread evenly between all task on any given day.
Right now, if I assign the same resource to all the task, I end up with 18h
workload days!!! I would like the 8h/day to be the fixed variable.
How do I do that?
Thanks.....
vbdev
I have what may seem a stupid question (new to Project):
I have a project with a lot of concurrent tasks. I have 1 single resource
only. I would like to assign that resource on each task, and I would like
the time to be spread evenly between all task on any given day.
Right now, if I assign the same resource to all the task, I end up with 18h
workload days!!! I would like the 8h/day to be the fixed variable.
How do I do that?
Thanks.....
vbdev