D
dave
How can I display numerous tasks on the same line without splitting?
I have a 6 month project where I will be cycling different personnel for 3
week blocks. I want to be able to display this on a gnatt chart where each
"block" shows up on the same task line so when I look at each block I will
see the person who is assigned to that 3 week block and not just the 6 month
duration.
Example
X Engineer ------------I have 6 different X Engineers I will be using. I
want to be able to attach a resource "by name" to each X Engineers duration
on the same line. My desire is when I right click on the each box on the same
line and look at "task information" I will see different names and the
duration will only be when the engineer by name is on site.
Next line
Y Engineer............. have 5 different Y Engineers I will be using. I want
to be able to attach a resource "by name" to each Y Engineers duration on the
same line.
etc....
Did I confuse everyone??
I have a 6 month project where I will be cycling different personnel for 3
week blocks. I want to be able to display this on a gnatt chart where each
"block" shows up on the same task line so when I look at each block I will
see the person who is assigned to that 3 week block and not just the 6 month
duration.
Example
X Engineer ------------I have 6 different X Engineers I will be using. I
want to be able to attach a resource "by name" to each X Engineers duration
on the same line. My desire is when I right click on the each box on the same
line and look at "task information" I will see different names and the
duration will only be when the engineer by name is on site.
Next line
Y Engineer............. have 5 different Y Engineers I will be using. I want
to be able to attach a resource "by name" to each Y Engineers duration on the
same line.
etc....
Did I confuse everyone??