Multiple Timelines in Tasks

K

koolkat

Is there a way to show multiple timelines in the same task? I've tried using
Base Start and Finish dates, etc.
 
J

John

koolkat said:
Is there a way to show multiple timelines in the same task? I've tried using
Base Start and Finish dates, etc.

koolkat,
You're going to have to be a little more specific. What exactly do you
mean by "multiple timelines"?

If you mean you want to show multiple independent Gantt bars on one task
line, then no, Project can't do that. The best it can do is to split a
single task into several sections. To find out how to do that, look up
"split task" in Project's help file.

John
Project MVP
 
J

Jim Aksel

Did you try View/More Views.. and select Multiple Baseline Gantt?
You would need to have baselines set with different days.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 