Hi,
how to setting one resource reporting to 2 timesheet manager.
Bill as a team member of A Project and B Project.
i want Bill will report his timesheet to every timesheet manager.
Tasks A Project will approve by A TimeSheet Manager and
Tasks B Project will approve by B TimeSheet Manager.
can anyone help me?

thank

reza
 
D

Dale Howard [MVP]

Reza --

In Project Server 2007, there are two types of approval managers. For the
hours that a resource enters into the My Timesheet page, there is a single
Timesheet Manager specified for that resource by editing the resource's
information from the Resource Center page. For the hours that a resource
enters into the My Tasks page, there is a Status Manager for the tasks in
each project. This means that the project manager of Project A approves the
task updates for tasks in his/her project, while the project manager of
Project B approves the task updates for tasks in his/her project.

Based on what I think you are asking, when a resource enters time on the My
Timesheet page, there is a single Timesheet Manager who approves the time
for both Project A and Project B. There is no way to change that. Hope
this helps.
 