Hi Steve
Thank you very much for your detailed response. It certainly helps in
getting my head around some of the definitions. One clarification and
one
question remain.
My 24 hr resource is computer time. We have multiple servers that I
need
to
assign as resources to a project. My manpower I have on an 8 hr
calendar
Question. It is possible to specify three types of calendars (perhaps
it's
only two),
The first is the project calendar, which is used to convert days work
to
minutes. The second is the resource calendar, which specifies work
hours
per
day for a resource. It is also possible to specify a project calendar
specific to a task (in the task details dialogue boxes), but I have no
idea
how the latter influences anything. It does not seem to make any
difference
in the final outcome. Perhaps you could provide some insights.
Many thanks
Jens
:
The base unit of duration is the minute. "Days" are allowed in user
input
and display for convenience but are converted to and from hours, thus
minutes, according to the conversion factor on the Tools Options
Calendar
page. If it helps, start thinking of "day" as meaning "workday," a
single
normal 8-hour work shift, rather than a calendar day and when
estimating
durations think in terms of the number of shifts the tasks will
require.
Thus a one calendar day task lasting 24 hours start-to-finish,
starting
Monday at 8am and finishing Tuesday at 8am, takes 3 8-hour shifts or 3
consecutive workdays to complete. If entering and keeping track of
the
tasks is becoming too complicated, start estimating work efforts in
hours
to
begin with.
You say you are hoping for duration to be equal to the physical number
of
calendar days. Sorry, you just can't have that. Project time is
measured
in either elapsed time or duration time. Elapsed time is the sort of
time
watches and conventional calendars measure. The month of November has
30
days, 720 hours. But duration is specifically defined as the number
of
working time units between two points (see PMBOK definitions) and any
non-working time is explicitly excluded from the measure. In the US
and
assuming a normal 8 hour workday, the month of November has 20, 21, or
22
work days (22 weekdays minus 1 or 2 day Thanksgiving holiday) giving
it a
duration of 160, 168 hours, or 174 hours depending on where you are.
I'd suggest examining your 24 hour calendar resources to see if that's
really accurate. The 24 hour calendar means that once the resource
starts
work, that specific individual worker doesn't take a break until the
work
is
done, regardless of whether the task takes hours, days, weeks, or even
months to complete. People just don't do that.
I'll bet what you're thinking here is that you have, say, a group of
10
welders, some on days, some of swing, some on graveyard with a base
calendar
of the 24 hour calendar assigned to the group. You have a welding
task
that
will take one person 24 hours to do so you're putting 1 day shift, 1
swing
shift, and 1 graveyard guy on it, each one relieving the guy before
him
and
working until the task is done. There are all kinds of problems with
that -
calendar problems are one but also resource allocation and tracking
max
allocations as well. I'd suggest a possible better way is to have 3
separate resource listings - Day Shift Welders, max 400%, base
calendar
8am-5pm; Swing Shift Welders, max 300%, base calendar 3pm-12mid; Night
Shift
Welders, max 300%, base calendar 11pm-8am. You have a task that will
take
24 man-hours work and you need to get it done in one continuous
stretch
of
work going on steadily from start to finish so it gets done ASAP.
Enter
the
task with 3 days duration. Use the split screen to assign the
resources.
Enter all three resources -- Day, Swing, & Grave -- with an
assignment
of
100% meaning one guy from each of the 3 shifts and give them 8 hours
work
each. Duration will still be 3 days, ie, 3 shifts, but the task will
go
24/7 until done and take 1 calendar day in the schedule.
Hope this helps
--
Steve House [MVP]
MS Project Trainer/Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
Hi Gerard
I think I am OK on the relationship between work and duration. What
I
was
hoping to do was for duration to be the physical number of caendar
days
the
task takes. The problem I have is that a 21 day duration task only
takes 7
calendar days if I assign a 24 hr resource to a project with an 8hr
calendar.
This makes it very messy when trying to assign work in days, and
using
both
8hr and 24hr resources.
I guess what I need is multiple project calendars that would be used
to
caluclate the hourly work effort depending on resource type when
entering
the
work effort in days.
Am I asking too much of Project, and am I doomed to have to imput
work
effort in hrs?
Thanks
Jens
:
Hello Jens,
If the resource(s) on the task are running with a 24 hr calendar
and
if
the
general setting of Project is Tools / Options / Calendar : Hours
per
day
:
8,00 then the "9 days" task will end after 3 days (24 x 3 = 72h).
Don't
confuse Duration and Work.
GÃf©rard Ducouret [Project MVP]
"Jens" <
[email protected]> a Ãf©crit dans le message
de
I am running multiple calenders for my resources, human resources
run
on a
normal calendar and non-human resources run 24 hr calendars. On
fixed
work
tasks, I would task a 24 hr calendar resouce with e.g. 9 days
work,
the
estimated duration is listed as 9 days?, but the finish date is
only
3
days
after the start as it uses the standard calender for it's
calculations.
I
am
trying to avoid artificially increasing the work entered (as it
affects
the
costing) but would like to see the finish date calculated
correctly,
i.e.
plus 9 days.
Any ideas?