Multiple Working Time

B

Bruce K.

Is there a way to have more than one "Working Time" calendar in the same
schedule file? Example; one part of the schedule the tasks will 18 hours a
day. Later in the schedule it is to 8 hours a day.

Bruce K.
 
J

Jan De Messemaeker

Hi,

Certainly. You can make another base calendar and connect that to the tasks
with a deviating working time (task information, advanced, or insert the
column Task Calendar)

HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620