Ken Kast
I have a situation where I have two tasks, with a different resource
assigned to each. I want the tasks to start when both resources are
available. I tried a StoS link, but that gives me effectively a NET
condition on the successor. What I'm looking for is a simultaneous NET and
NLT based on resource availability. Is there anyway to model this in
Project?
Thanks.
Ken