Hi,

when I select "Timephased View" in "My Assignments" only actual work is
shown, but no scheduled work.
However, if I move the mouse over a cell which should contain planned work
this values is displayed in a tool tip.
Is this a known issue?
Is there a way to display scheduled work on a daily basis in this view?

Kind regards

Rolf
 
D

Dale Howard [MVP]

Rolf --

This is not a bug; it is by design. There is no way to display planned work
on the My Tasks page. Hope this helps.
 
R

rolfb

Hi Dale,

yes and no.
Yes as the software is working correctly and no as our team is requesting
this information.

Is there an easy way to get a daily assignemnt overview for team members?

Kind regards

Rolf
 
D

Dale Howard [MVP]

Rolf --

Yes and no? I didn't ask you any questions. And if you are asking if there
is a way to show planned Work on the My Tasks page, the answer is still no.
Hope this helps.
 