Pei
I have created a master project with links to multiple projects. Everytime I
open the master project, the dates are not correct. It corrects itself only
if I uncollapse and collapse each project again manually.
I also want to save an unlinked version of this master project on a weekly
basis to track changes. When I remove the link to the individual projects,
the dates revert to the wrong dates again.
It only does this for some individual projects but not all (about 10 of 20).
I have not been able to work out what differences these projects have
compared to the others.
open the master project, the dates are not correct. It corrects itself only
if I uncollapse and collapse each project again manually.
I also want to save an unlinked version of this master project on a weekly
basis to track changes. When I remove the link to the individual projects,
the dates revert to the wrong dates again.
It only does this for some individual projects but not all (about 10 of 20).
I have not been able to work out what differences these projects have
compared to the others.