My Task actual hour

R

Ron Bess

I am having an issue in the Project Plan where actual hour that were
imported from the timesheet into My Task page and approved by the project
manager does not appear in the project plan. Any suggestions?
ronb
 
D

Dale Howard [MVP]

Ron --

This was a known bug prior to Service Pack 1 for Project Server 2007. Is
your Project Server 2007 system updated with the latest Service Packs and
Cumulative Updates? Let us know and we will try to help.
 