MY Task

A

Alia BinHafiz

Thank you Ben for your quick respond... is there any specific felid do i have
to check.. because i check his profile all necessary filed has been filled.
and he is the assignment owner for all his task.. i need your help
 
D

DogLBer

Have him review and uncheck "Show Only Current Tasks" in the My Tasks view
options. The task start date may be outside the limits.
 
A

Alia BinHafiz

Thank you for your quick respond the problem is We are using Project Server
2007 in our organisation and one of the users can not see his current task
assignments in the My Task screen. These assignments can be see in the
project plan as well as Resource Assignment , But not in the My Task screen.
Can anyone help me please.
 
J

.jussi

Hi Alia,

Check these:
* Tasks have the "publish" field set (you may have to add the field to a
view in Project Pro to see this)
* Project is published
* The user has the proper permissions set ("my tasks" through either through
group membership or security categories)

Are you using active directory to synchronize your users? If so, double
check that the user is in the right group in the AD.

Hope that helps,
- Jussi
 
C

Chet

One other thing to check is the Resource's "Booking Type." The resource
needs this set to "Committed" to see the tasks on the My Task page. If set
to "Proposed" the tasks won't appear.

In MS Project go to the Resource Sheet view and insert the column "Booking
Type." You can change it there if need be.
 