My Tasks: An Unexpected Error Has Occurred even after SP1 installa

J

Joao Cortez

Hello,

We have observed this problem since we first migrated to Project Server
2007. Some users (we do not have a good pattern yet) get the error: "An
Unexpected Error Has Occurred" when they go to "My Tasks".

We have applied both the SP1 and the Post-Service Pack 1 Hot-fix package and
we are still facing the same problem. This is really a pain.

Any help?

Thanks & Regards,
João
 
P

Peter M.

First, sorry I cannot help you.

But, I have the same exact problem here, too und would greatly appreciate
any help concerning this.
Thanks to everyone.

Regards,
Peter
 
P

Peter M.

Hi João,
I have gained new insights about this very issue recently. As it seems, the
error described occurs when resources get assigned to a task that another
resource is assigned to already and has already submitted actual work time.
This may happen when resources reassign tasks to other resources while having
already entered actual work time.
This is a bug and I believe that the only way so far to resolve it is to
simply ask the project manager to close the affected task and reassign it to
the new resource/s.

I hope this helped you.

Regards,
Peter
 