How can I change the units users enter for their actual/remaining work from
days to hors when they enter them from the My tasks Menu in PWA.
Hi Kalin,
Go to My Tasks page and click on Site Actions menu then Edit Page.
Now, you can see the My Tasks grid (webpart) showing up in edit mode.
Now, click on the down arrow at top right corner of the web part and
choose edit. You will see a properties window at right hand side and
scroll down and collapse PWA section. There you can find options to se
the work format from days to hours.
Thanks,
Ravi.