My Tasks > Go to > Tasks Gantt View

R

Robert

Hello,
In my English version of PWA 2007 SP1, the sequence menu My Tasks > Go to >
Tasks Gantt View works fine : I get the Resource Assignments page.
In my French version of PWA 2007 SP1, the equivalent of Tasks Gantt View
(Affichage de Gantt pour les tâches) is greyded out.
Why ?
Thanks for your help
 
R

Robert

Gary,
These are two separate instances on two separate domains.
Where and how can we turn on /off this feature?
Thanks again
 
S

Sander

The option is called (in english :)):
" Enable Team Member Gantt view "