A
AmWall
I am using Project Server 2007, pre-SP1. But have recently installed the
Hotfix kb/937476/ for My Tasks that provides the total for time resource adds
to tasks.
The problem we are experiencing deals with the dates displayed for the tasks
in the My Assignments and Timesheet view where the resource is supposed to
enter their time. We want the dates to display Sunday thru Saturday, but they
seem to be changing from this to Week starting Friday thru Thursday. How can
we always have the view display Sunday thru Saturday?
Hotfix kb/937476/ for My Tasks that provides the total for time resource adds
to tasks.
The problem we are experiencing deals with the dates displayed for the tasks
in the My Assignments and Timesheet view where the resource is supposed to
enter their time. We want the dates to display Sunday thru Saturday, but they
seem to be changing from this to Week starting Friday thru Thursday. How can
we always have the view display Sunday thru Saturday?