My Tasks new view (filtered)

O

OK

Please explain how to filter tasks (My Tasks) to see only tasks for projects
with the custom field (In Progress)?
When creating a new view (My Work) I don't see any filter ....
 
A

Andrew Lavinsky

You can't filter My Tasks. You can however opt not to publish tasks that
have the custom field set to no - generally through the use of a macro in
the MPP file.

Check out the usage of the Publish field.


- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm
 
G

Gary Chefetz

We have a web part that allows you to apply a constant filter to the My
Tasks page, but you cannot apply it to a specific view. If you're
interested, you can download a trial version at our site
https://www.projectdaddy.com
 