Hello, I have created a custom task field that our project managers populate
when creating the plan in Project Professional 2007. However, when you open
My Tasks to view the tasks assigned the popluated data did not come over into
the custom field. I can enter data into the custom field within My Tasks page
, but when you save and submit nothing happens with the data you entered. So
my expereince to date is custom fields within My Tasks or My Timesheet does
not provide much value. We have Sp1 installed.
Has anyone else seen this...? Or has a workaround...?
Jason
when creating the plan in Project Professional 2007. However, when you open
My Tasks to view the tasks assigned the popluated data did not come over into
the custom field. I can enter data into the custom field within My Tasks page
, but when you save and submit nothing happens with the data you entered. So
my expereince to date is custom fields within My Tasks or My Timesheet does
not provide much value. We have Sp1 installed.
Has anyone else seen this...? Or has a workaround...?