Hi guys,

I had a few questions in relation to the My Tasks view in Project
Server 2007. Is it possible to change the default time period? Right
now it is currently going to the next week when you go into the My
Tasks web part. For example, it opens to the week of Dec. 28th right
now.

My other question is if there is a way to show the total hours entered
like the timesheets do. So if a resource enters their time for the
week they don't have to add the days together across their assignments
to make sure they entered 40 hours.

Thanks for your help!
 
R

Robert

The Actual work column will show hrs published to the plans and is useful for
seeing what has been previously published to the task.
As far as the current week goes it should be default be on the current week.

Are you entering hrs by the week instead of by day? As an example we have
the week starting on Sundays and our My Tasks show 12/13 12/20 12/27 1/3
so not sure why you are seeing only 12/28.
Are you you using the Timephased View in the webpart?




--
Project Consultant

REJ Company

(e-mail address removed)
 
B

Bryan

The Actual work column will show hrs published to the plans and is usefulfor
seeing what has been previously published to the task.
As far as the current week goes it should be default be on the current week.

Are you entering hrs by the week instead of by day? As an example we have
the week starting on Sundays and our My Tasks show  12/13  12/20  12/27  1/3
so not sure why you are seeing only 12/28.
Are you you using the Timephased View in the webpart?

--
Project Consultant

REJ Company

(e-mail address removed)

I have it set for hours per day starting on Saturday in a timephased
view. So when I click on My Tasks it shows me the week of 12/28 and I
need to click Previous to get to this week.

I was hoping there was a way to show the total hours currently entered
for the week (like in the My Timesheets page). We do not use
timesheets at all--only Task updates.
 
D

Dale Howard [MVP]

Bryan --

A training client of ours had a similar problem, which was caused by setting
Saturday as the starting day of the My Tasks page. On the client's system,
the My Tasks page always showed the NEXT week rather than the current week.
When the client set either Sunday or Monday as the starting day, the My
Tasks page showed the current week as expected. If you select Sunday or
Monday, does the My Tasks page show the current week? Let us know.
 
B

Bryan

Bryan --

A training client of ours had a similar problem, which was caused by setting
Saturday as the starting day of the My Tasks page.  On the client's system,
the My Tasks page always showed the NEXT week rather than the current week.
When the client set either Sunday or Monday as the starting day, the My
Tasks page showed the current week as expected.  If you select Sunday or
Monday, does the My Tasks page show the current week?  Let us know.

I changed the start date to Sunday and it solved the problem! Thanks
Dale!

Any chance I can show the total hours entered (saved) for the week in
the My Tasks page? Somehow I don't think so but thought it is worth
asking.
 
D

Dale Howard [MVP]

Bryan --

I am pleased that my client's pain turned into your gain! To answer your
second question, there is no default way to add totals at the bottom of the
My Tasks page; on the other hand, you CAN add totals by adding the My Task
Totals web part to your organization's My Tasks page. You can learn more
about this Web part at the following URL:

https://www.projectdaddy.com/shopexd.asp?id=482

Our company has a variety of other very useful Web parts that effectively
"tame" and enhance the user experience on the My Tasks page. Hope this
helps.
 
J

JennPenn07

Dale, we also start our weeks on Saturday and have the same problem. Did you
client ever find a resolve to thier issue. I would rather not change the
week's start day.

Thanks,

Oh and I have trialed the task totals web part and we like it. Personally,
i like that we can watch our totals without having to scroll to the bottom of
the tasks. Very cool.
 
D

Dale Howard [MVP]

JennPenn07 --

I am not aware of any way to work around the problems caused by setting
Saturday as the start of the timesheet grid in the My Tasks page. Sorry.
But I am glad you like the Web part! :)




JennPenn07 said:
Dale, we also start our weeks on Saturday and have the same problem. Did
you
client ever find a resolve to thier issue. I would rather not change the
week's start day.

Thanks,

Oh and I have trialed the task totals web part and we like it.
Personally,
i like that we can watch our totals without having to scroll to the bottom
of
the tasks. Very cool.

Dale Howard said:
Bryan --

I am pleased that my client's pain turned into your gain! To answer your
second question, there is no default way to add totals at the bottom of
the
My Tasks page; on the other hand, you CAN add totals by adding the My
Task
Totals web part to your organization's My Tasks page. You can learn more
about this Web part at the following URL:

https://www.projectdaddy.com/shopexd.asp?id=482

Our company has a variety of other very useful Web parts that effectively
"tame" and enhance the user experience on the My Tasks page. Hope this
helps.




Bryan said:
On Dec 22, 2:36 pm, "Dale Howard [MVP]" <dale[dot]howard[at]
msprojectexperts[dot]com> wrote:
Bryan --

A training client of ours had a similar problem, which was caused by
setting
Saturday as the starting day of the My Tasks page. On the client's
system,
the My Tasks page always showed the NEXT week rather than the current
week.
When the client set either Sunday or Monday as the starting day, the
My
Tasks page showed the current week as expected. If you select Sunday
or
Monday, does the My Tasks page show the current week? Let us know.





Hi guys,

I had a few questions in relation to the My Tasks view in Project
Server 2007. Is it possible to change the default time period?
Right
now it is currently going to the next week when you go into the My
Tasks web part. For example, it opens to the week of Dec. 28th
right
now.

My other question is if there is a way to show the total hours
entered
like the timesheets do. So if a resource enters their time for the
week they don't have to add the days together across their
assignments
to make sure they entered 40 hours.

Thanks for your help!

I changed the start date to Sunday and it solved the problem! Thanks
Dale!

Any chance I can show the total hours entered (saved) for the week in
the My Tasks page? Somehow I don't think so but thought it is worth
asking.
 
B

Bryan

JennPenn07 --

I am not aware of any way to work around the problems caused by setting
Saturday as the start of the timesheet grid in the My Tasks page.  Sorry.
But I am glad you like the Web part!  :)




Dale, we also start our weeks on Saturday and have the same problem.  Did
you
client ever find a resolve to thier issue.  I would rather not changethe
week's start day.

Oh and I have trialed the task totals web part and we like it.
Personally,
i like that we can watch our totals without having to scroll to the bottom
of
the tasks.  Very cool.
Bryan --
I am pleased that my client's pain turned into your gain!  To answeryour
second question, there is no default way to add totals at the bottom of
the
My Tasks page; on the other hand, you CAN add totals by adding the My
Task
Totals web part to your organization's My Tasks page.  You can learnmore
about this Web part at the following URL:
https://www.projectdaddy.com/shopexd.asp?id=482
Our company has a variety of other very useful Web parts that effectively
"tame" and enhance the user experience on the My Tasks page.  Hope this
helps.

On Dec 22, 2:36 pm, "Dale Howard [MVP]" <dale[dot]howard[at]
msprojectexperts[dot]com> wrote:
Bryan --
A training client of ours had a similar problem, which was caused by
setting
Saturday as the starting day of the My Tasks page.  On the client's
system,
the My Tasks page always showed the NEXT week rather than the current
week.
When the client set either Sunday or Monday as the starting day, the
My
Tasks page showed the current week as expected.  If you select Sunday
or
Monday, does the My Tasks page show the current week?  Let us know.


Hi guys,
I had a few questions in relation to the My Tasks view in Project
Server 2007.  Is it possible to change the default time period?
Right
now it is currently going to the next week when you go into the My
Tasks web part.  For example, it opens to the week of Dec. 28th
right
now.
My other question is if there is a way to show the total hours
entered
like the timesheets do.  So if a resource enters their time forthe
week they don't have to add the days together across their
assignments
to make sure they entered 40 hours.
Thanks for your help!
I changed the start date to Sunday and it solved the problem!  Thanks
Dale!
Any chance I can show the total hours entered (saved) for the week in
the My Tasks page?  Somehow I don't think so but thought it is worth
asking.

Thanks for the tips Dale! We did go ahead and purchase the web part
and is great. Thanks so much for all of your help!
 