My Tasks showing 2 Views in the window

B

Bonnie

After using site actions to change the MY TASKS display to show as hours
rather than days, users are reporting having 2 "views" appearing in the My
Tasks window. The heading even shows "My Tasks (2)".

This does not occur on my or other admin's views. But, the other users all
see this double view in the window.

Any ideas how to address this?
 
B

BruceFFIC

After using site actions to change the MY TASKS display to show as hours
rather than days, users are reporting having 2 "views" appearing in the My
Tasks window.  The heading even shows "My Tasks (2)".

This does not occur on my or other admin's views.  But, the other usersall
see this double view in the window.

Any ideas how to address this?

We had this happen at our site, but for timesheets. It happend when
we reset the Timesheet Webpart, and those users who had personalized
their Timesheet Webpart starting showing two Timesheet Webparts.
These were the steps we used to fix it:

1) Open up any timesheet to view your My Timesheets page
2) Click the drop-down arrow next to the Welcome (Your Name) message
in the upper-right
corner of your screen to see a list of options
3) Click Reset Page Content.
4) You will get a message to confirm -- click OK

Hope this helps.
 