my tasks shows incorrect actual work time in PWA 2007

C

c5solutions

I have the following problem and for now still have no clue what it might
come from:
it happens for some resources on some tasks that they enter work in the my
tasks view and for some reason the work entered in those fields is
"smoothened" when you view it again later. for example, for one task I
entered the values
(mon ; tue ; wed ; thu ; fri)
2h ; 3h ; 0h ; 1.5h ; 7h
and if I review them in the (same) my tasks view they become
1.75h ; 2.875h ; 0.375h ; 1.313h ; 6.313h
so for some reason, which I dont understand, the time entered is distributed
on the whole week... whilst there is still a similarity between the entered
time and what is shown... I think in most cases the sum actually is the same.
Most surprisingly, the times dont seem to be saved like this anyway... when
you create a timesheet, which automatically fills in the previously entered
actual work,
the values are all correctly as entered first (2h ; 3h ; 0h ; 1.5h ; 7h)

any help or ideas on this would be greatly appreciated
 
C

c5solutions

here restarting the servers in the farm seems to have resolved the issue...
what a crazy software project 2007 seems to be...
 