We are using Server 2007 with SP1 and Feb CU, resource is attempting to enter
time to a task in PWA but the time entered will not remain no matter whether
save, recalculate, submit or submit all are chosen. Resource is NOT moving
to previous or next week in browser. Have had resource clear cache in
browser and ensure trusted site. Only single task encountering issue and
others keep time in browser. Have been able to enter time to this specfic
task before, resource not contoured, did put H after the time entry, Task is
open and not closed to updates, Resource is Active. I'm out of root
causes..anyone else experience this on a single task in a plan for a single
resource on a task with multiple resources?
time to a task in PWA but the time entered will not remain no matter whether
save, recalculate, submit or submit all are chosen. Resource is NOT moving
to previous or next week in browser. Have had resource clear cache in
browser and ensure trusted site. Only single task encountering issue and
others keep time in browser. Have been able to enter time to this specfic
task before, resource not contoured, did put H after the time entry, Task is
open and not closed to updates, Resource is Active. I'm out of root
causes..anyone else experience this on a single task in a plan for a single
resource on a task with multiple resources?