We are using My Tasks view for timesheet filling in PS 07. Pls suggest me the
ways how to restrict resources logging in manhours against a particular task.
For example... we as a team are working on a proposal. After 1 wk let us say
I have to restrict one out of the two Process Engineers logging manhours in
this particular proposal. Pls suggest me a way to do this.
Thanks,
3vikram.
ways how to restrict resources logging in manhours against a particular task.
For example... we as a team are working on a proposal. After 1 wk let us say
I have to restrict one out of the two Process Engineers logging manhours in
this particular proposal. Pls suggest me a way to do this.
Thanks,
3vikram.