We created a custom view for My Tasks and the values for enterprise custom
fields are not appearing in the view. The columns show but there are no
values although there are values in the timeline itself. Oddly enough we can
add values into the fields via My Tasks, save and publish but we cannot get
the values from the Project client to display on publish.

Any ideas?
 
D

Dale Howard [MVP]

chicagohunter --

When your Project Server administrator created these custom enterprise
fields, did he/she remember to select the "Roll down, unless manually
specified" option for each field? After creating these fields, did each PM
open his/her projects, specify a value for each task in each of these
fields, and then publish the latest changes to their schedules? Let us know
and we will try to help.
 
C

chicagohunter

Thank was exactly the issue Dale - the enterprise fields were set to 'None'
instead of Roll Down. Thanks for your help.
 