Immediately it quit updating any field except the hours. We had text and
date fields that would be set by the user to indicate status. When the Dec CU
was applied it quit passing or receiving data in those fields. Ie. a Status
field change of incomplete to on schedule would not update the project.
Conversely changes introduced to the project plan will not appear in the MY
Tasks view, but those changes introduced in the project plan will appear in a
Prject Center view. We are using Enterprise fields for the updates but I have
also tested it with non-enterprise fields with the same results.
Updates to hours are working fine.
Has anybody else seen these symptoms with Dec CU?
 
D

DogLBer

We opened a case and it is resolved. According to the MS Tech after Oct
Update updates should be made using the Resource Usage view not the Gantt
view. It works.
 