Project Server 2007 w/July 2008 Infrastructure Update
WSS 3.0 w/July 2008 Infrastructure Update
We recently added an Enterprise Custom Field, Charge Code, for tracking
information at the task level. PMs populate the Charge Code before
publishing the project to the server.
Our Timesheet component is configured to autopopulate using current Tasks
during the "Create Timesheet" process. When I create a new Timesheet, the
Charge Code field is populated correctly for currently assigned tasks.
However, if I use the "Add Lines" feature to add a separate Task to my
Timesheet, the Charge Code field is empty.
Am I seeing the behavior of a bug, lack of process flow to support what I
want, or something else? Any recommendations are greatly appreciated.
===========
Gina Montgomery
WSS 3.0 w/July 2008 Infrastructure Update
We recently added an Enterprise Custom Field, Charge Code, for tracking
information at the task level. PMs populate the Charge Code before
publishing the project to the server.
Our Timesheet component is configured to autopopulate using current Tasks
during the "Create Timesheet" process. When I create a new Timesheet, the
Charge Code field is populated correctly for currently assigned tasks.
However, if I use the "Add Lines" feature to add a separate Task to my
Timesheet, the Charge Code field is empty.
Am I seeing the behavior of a bug, lack of process flow to support what I
want, or something else? Any recommendations are greatly appreciated.
===========
Gina Montgomery