Running Project Server 2007 with SP 1:
We have a need to include task information that is being stored in a text
field into a custom My Work View (My Tasks). The data (content of the field)
is not being displayed when the My Work view is used to view My Tasks.
The content of this text field is being displayed on a custom Project View
where the text field has been included.
I have tried creating an Enterprise Custom Text field with the same results.
Is this a "bug" or am I doing something wrong?
We have a need to include task information that is being stored in a text
field into a custom My Work View (My Tasks). The data (content of the field)
is not being displayed when the My Work view is used to view My Tasks.
The content of this text field is being displayed on a custom Project View
where the text field has been included.
I have tried creating an Enterprise Custom Text field with the same results.
Is this a "bug" or am I doing something wrong?