J
J Burford Fields
One of our project managers, reviewing her time entered in PWA, found
time charged to a task on which she has never worked. The task only
apears in PWA, for her, because I added her as a resource to all tasks
on that project at a 0% level of effort so that she might adjust
remaining hours, someday in the future.
The hours that she is seeing had to have been entered by another
resource.
The only thing that I think might explain this behavior is that it was
discovered that she had created some additional tasks, in the same
project, that weren't authorized after the project was baselined.
Those tasks were deleted. We later learned that resources had entered
time against them, but there was no warning message. Probably the task
owner, or the person who republished and became a task owner, had not
accepted the time entries prior to the task deletion, but did so later.
While it took unusual circumstances to create this, it is not good that
time entered by anyone else should ever show up in ones own actuals.
Any thoughts?
time charged to a task on which she has never worked. The task only
apears in PWA, for her, because I added her as a resource to all tasks
on that project at a 0% level of effort so that she might adjust
remaining hours, someday in the future.
The hours that she is seeing had to have been entered by another
resource.
The only thing that I think might explain this behavior is that it was
discovered that she had created some additional tasks, in the same
project, that weren't authorized after the project was baselined.
Those tasks were deleted. We later learned that resources had entered
time against them, but there was no warning message. Probably the task
owner, or the person who republished and became a task owner, had not
accepted the time entries prior to the task deletion, but did so later.
While it took unusual circumstances to create this, it is not good that
time entered by anyone else should ever show up in ones own actuals.
Any thoughts?