NA value in Finish field

K

Kesari Suresh

Hi
Pleas help me to insert a NA or N/A value in finish field.
Wheni first create a task i want my task finish and start dates to be null,
so that i can enter them manually through PWA.
Is this possible.

Please help me.

Regards,
Kesari Suresh.
 
J

JulieS

Hi Kesari Suresh,

I'm afraid neither the start nor the finish fields can be null in
Project. Perhaps what you are seeking is the [Actual Start] and [Actual
Finish] fields. They are NA until tracking data is supplied to the
project file.

--
I hope this helps. Let us know how you get along.

Julie

Visit http://project.mvps.org/ for FAQs and more information about
Microsoft Project.
 
×

יו×ב שוחט

You can define 2 Enterprise date fields. The default for those is NA.
Now define a macro that when accepting the dates and opening the project in
the Professional (on open project event) those dates are copied to
Start/Finish fields.

JulieS said:
Hi Kesari Suresh,

I'm afraid neither the start nor the finish fields can be null in
Project. Perhaps what you are seeking is the [Actual Start] and [Actual
Finish] fields. They are NA until tracking data is supplied to the
project file.

--
I hope this helps. Let us know how you get along.

Julie

Visit http://project.mvps.org/ for FAQs and more information about
Microsoft Project.

Kesari Suresh said:
Hi
Pleas help me to insert a NA or N/A value in finish field.
Wheni first create a task i want my task finish and start dates to be
null,
so that i can enter them manually through PWA.
Is this possible.

Please help me.

Regards,
Kesari Suresh.
 
K

Kesari Suresh

HI,
Thanks alot for your reply.
Iam having another serious problem.
I have to save finish dates before changing them so that i can prepare a
report of old finish dates and new finish dates submitted by team members.
Can you please me on this issue also. If this needs a formula or any thing
like that can you please elaborate.

Thanks and regards,
Kesari suresh

יו×ב שוחט said:
You can define 2 Enterprise date fields. The default for those is NA.
Now define a macro that when accepting the dates and opening the project in
the Professional (on open project event) those dates are copied to
Start/Finish fields.

JulieS said:
Hi Kesari Suresh,

I'm afraid neither the start nor the finish fields can be null in
Project. Perhaps what you are seeking is the [Actual Start] and [Actual
Finish] fields. They are NA until tracking data is supplied to the
project file.

--
I hope this helps. Let us know how you get along.

Julie

Visit http://project.mvps.org/ for FAQs and more information about
Microsoft Project.

Kesari Suresh said:
Hi
Pleas help me to insert a NA or N/A value in finish field.
Wheni first create a task i want my task finish and start dates to be
null,
so that i can enter them manually through PWA.
Is this possible.

Please help me.

Regards,
Kesari Suresh.
 
J

JulieS

Hi Kesari Suresh,

From your description I think you are looking for Baseline data. Before
your resources begin to supply you with Actual Data, save a baseline in
Project Professional. (Tools > Tracking > Save Baseline.) This will
copy your planned start and finish dates from the schedule into Baseline
Start and Baseline Finish.

As your resource begin to modify Actual Start and Actual Finish through
tracking, you can compare Baseline Start to Actual Start through the
Start Variance field and Baseline Finish to Actual Finish through the
Finish Variance field.

--
I hope this helps. Let us know how you get along.

Julie

Visit http://project.mvps.org/ for FAQs and more information about
Microsoft Project.
Kesari Suresh said:
HI,
Thanks alot for your reply.
Iam having another serious problem.
I have to save finish dates before changing them so that i can prepare
a
report of old finish dates and new finish dates submitted by team
members.
Can you please me on this issue also. If this needs a formula or any
thing
like that can you please elaborate.

Thanks and regards,
Kesari suresh

???? ???? said:
You can define 2 Enterprise date fields. The default for those is NA.
Now define a macro that when accepting the dates and opening the
project in
the Professional (on open project event) those dates are copied to
Start/Finish fields.

JulieS said:
Hi Kesari Suresh,

I'm afraid neither the start nor the finish fields can be null in
Project. Perhaps what you are seeking is the [Actual Start] and
[Actual
Finish] fields. They are NA until tracking data is supplied to the
project file.

--
I hope this helps. Let us know how you get along.

Julie

Visit http://project.mvps.org/ for FAQs and more information about
Microsoft Project.

message Hi
Pleas help me to insert a NA or N/A value in finish field.
Wheni first create a task i want my task finish and start dates
to be
null,
so that i can enter them manually through PWA.
Is this possible.

Please help me.

Regards,
Kesari Suresh.
 
×

יו×ב שוחט

Copy by macro the start and finish dated to Enterprise date fields.
Use the record button to build the macro. as simple as that....

Kesari Suresh said:
HI,
Thanks alot for your reply.
Iam having another serious problem.
I have to save finish dates before changing them so that i can prepare a
report of old finish dates and new finish dates submitted by team members.
Can you please me on this issue also. If this needs a formula or any thing
like that can you please elaborate.

Thanks and regards,
Kesari suresh

יו×ב שוחט said:
You can define 2 Enterprise date fields. The default for those is NA.
Now define a macro that when accepting the dates and opening the project in
the Professional (on open project event) those dates are copied to
Start/Finish fields.

JulieS said:
Hi Kesari Suresh,

I'm afraid neither the start nor the finish fields can be null in
Project. Perhaps what you are seeking is the [Actual Start] and [Actual
Finish] fields. They are NA until tracking data is supplied to the
project file.

--
I hope this helps. Let us know how you get along.

Julie

Visit http://project.mvps.org/ for FAQs and more information about
Microsoft Project.

message Hi
Pleas help me to insert a NA or N/A value in finish field.
Wheni first create a task i want my task finish and start dates to be
null,
so that i can enter them manually through PWA.
Is this possible.

Please help me.

Regards,
Kesari Suresh.
 
K

Kesari Suresh

Hi
my issue would not be solved with baseline because there are chances that
the finish dates may be changed again and again. i believe the macro stuff
might work but i have no experience in writing macros. Can any one help me in
providing the steps to write a macro for solving this problem. if this is
done i can be relieved a lot.

Thanks in advance,
kesari suresh.

JulieS said:
Hi Kesari Suresh,

From your description I think you are looking for Baseline data. Before
your resources begin to supply you with Actual Data, save a baseline in
Project Professional. (Tools > Tracking > Save Baseline.) This will
copy your planned start and finish dates from the schedule into Baseline
Start and Baseline Finish.

As your resource begin to modify Actual Start and Actual Finish through
tracking, you can compare Baseline Start to Actual Start through the
Start Variance field and Baseline Finish to Actual Finish through the
Finish Variance field.

--
I hope this helps. Let us know how you get along.

Julie

Visit http://project.mvps.org/ for FAQs and more information about
Microsoft Project.
Kesari Suresh said:
HI,
Thanks alot for your reply.
Iam having another serious problem.
I have to save finish dates before changing them so that i can prepare
a
report of old finish dates and new finish dates submitted by team
members.
Can you please me on this issue also. If this needs a formula or any
thing
like that can you please elaborate.

Thanks and regards,
Kesari suresh

???? ???? said:
You can define 2 Enterprise date fields. The default for those is NA.
Now define a macro that when accepting the dates and opening the
project in
the Professional (on open project event) those dates are copied to
Start/Finish fields.

:

Hi Kesari Suresh,

I'm afraid neither the start nor the finish fields can be null in
Project. Perhaps what you are seeking is the [Actual Start] and
[Actual
Finish] fields. They are NA until tracking data is supplied to the
project file.

--
I hope this helps. Let us know how you get along.

Julie

Visit http://project.mvps.org/ for FAQs and more information about
Microsoft Project.

message Hi
Pleas help me to insert a NA or N/A value in finish field.
Wheni first create a task i want my task finish and start dates
to be
null,
so that i can enter them manually through PWA.
Is this possible.

Please help me.

Regards,
Kesari Suresh.
 
K

Kesari Suresh

HI,
My only problem is retaing one set of old date and new date, however many
time the date field is changed.
I do not want to manually save interim base plans every time. It has to be
done automatically.
Is it possible with formulas or macros. If so how can i do that. Can you
provide me with steps do do taht.
I tried macro but falied to access date field value from within macro...
Please help me

Regards,
Kesari Suresh.

יו×ב שוחט said:
Copy by macro the start and finish dated to Enterprise date fields.
Use the record button to build the macro. as simple as that....

Kesari Suresh said:
HI,
Thanks alot for your reply.
Iam having another serious problem.
I have to save finish dates before changing them so that i can prepare a
report of old finish dates and new finish dates submitted by team members.
Can you please me on this issue also. If this needs a formula or any thing
like that can you please elaborate.

Thanks and regards,
Kesari suresh

יו×ב שוחט said:
You can define 2 Enterprise date fields. The default for those is NA.
Now define a macro that when accepting the dates and opening the project in
the Professional (on open project event) those dates are copied to
Start/Finish fields.

:

Hi Kesari Suresh,

I'm afraid neither the start nor the finish fields can be null in
Project. Perhaps what you are seeking is the [Actual Start] and [Actual
Finish] fields. They are NA until tracking data is supplied to the
project file.

--
I hope this helps. Let us know how you get along.

Julie

Visit http://project.mvps.org/ for FAQs and more information about
Microsoft Project.

message Hi
Pleas help me to insert a NA or N/A value in finish field.
Wheni first create a task i want my task finish and start dates to be
null,
so that i can enter them manually through PWA.
Is this possible.

Please help me.

Regards,
Kesari Suresh.
 