Names under Adjust Actuals in 2003

R

Rob

I have a question regarding the Adjust Actuals.
If I enter time for a resource and submit that time why does my name not the
resources name show when the PM is accepting time for his or her plans? You
would think it would be the person on the plan. I see this a huge problem
when you have 5-6 people that you do adjust actuals for and they all are
listed under your name instead of theirs. Is this correct and if so is it
corrected in 2007.
 
A

ad9aggie

Rob,

My understanding of why this happens is because it is you submitting the
time for that person, so the time entered is coming in under your ID rather
than the other person's.

In the Updates section of PWA, there will be two different entries: Task
Update for timesheet entries, and Task Adjust for entries from Adjust
Actuals. The Assigned To field will show who the task entry is for.

Hope this helps,

Jonathan
 