L
Leslie Harmer
Hello. I would like to schedule a series of tasks that
each require the use of a certain machine. The machine is
only available at certain times. Only one task can use
the machine at a time. Thus, it may not matter how many
people I assign to a task, because progress can only be
made when the machine is available. How do I do this in
MS Project? (I am using MS Project Standard 2002.)
Thanks!
each require the use of a certain machine. The machine is
only available at certain times. Only one task can use
the machine at a time. Thus, it may not matter how many
people I assign to a task, because progress can only be
made when the machine is available. How do I do this in
MS Project? (I am using MS Project Standard 2002.)
Thanks!