Need a list of all Task Updates that have not been processed

G

Gary Zag

Using Project Server 2007. Is there a way for an administrator to see a
list of all the task updates, along with the date that they were submitted,
that have not been processed by all the project manager?

Gary
 
S

Sander

Hi Gary,

Nope, this is not available. I had this request once with a customer and had
to digg into the published database (not supported querying!!).
But then still it is not possible to get the number of hours of the not
processed task updates.

The way of working for this, is to have a data analysis view with baseline
work and actual work. If there is baseline work and no actual, you have a
'maybe not processed task update' or just a resource that has worked on
something else.


hope this helps.

Sander
 
G

Gary Zag

I don't need to know the hours that have not been accepted. We only want to
monitor that the project managers are accepting the updates in a timely
manner.

Gary
 