C
Carlos G
I have to set up some tasks on a "need by" basis. I have a
subcontract (SUB) that has a 52 week delivery schedule. I need the
delivery by the start of task ABC. To be safe, I want to give myself
a 4 week "buffer" which should be sufficient to cover the sub's
delays, based on prior experience.
I'm trying to figure out what the best way to set this up in Project
is.
I tried the standard "start as soon as possible". However, this moves
the tasks way too early, resulting in over a year of slack. Not at
all what I want - which makes sense, since I don't want to start as
soon as possible.
I then tried the "start as late as possible" constraint with a 30 day
lag to the successor task. This puts my task start where I want it.
However, it automatically tells me that I have 0 slack, and therefore
it is in the critical path. However, by design, I have built in 30
days reserve, so in reality I want to have Project show 30 day slack,
and remove it from the critical path.
What's the best way to setup this scenario?
Thanks!
Carlos
subcontract (SUB) that has a 52 week delivery schedule. I need the
delivery by the start of task ABC. To be safe, I want to give myself
a 4 week "buffer" which should be sufficient to cover the sub's
delays, based on prior experience.
I'm trying to figure out what the best way to set this up in Project
is.
I tried the standard "start as soon as possible". However, this moves
the tasks way too early, resulting in over a year of slack. Not at
all what I want - which makes sense, since I don't want to start as
soon as possible.
I then tried the "start as late as possible" constraint with a 30 day
lag to the successor task. This puts my task start where I want it.
However, it automatically tells me that I have 0 slack, and therefore
it is in the critical path. However, by design, I have built in 30
days reserve, so in reality I want to have Project show 30 day slack,
and remove it from the critical path.
What's the best way to setup this scenario?
Thanks!
Carlos