D
DWGLompoc
For a government customer, I need to show "duration" in calendar days not
work days. The big problem is with "Summary Tasks". I can easily set
individual tasks to calendar days be specifying, for example, 5 edays
(elapsed days). But the summary task is still displaying work days. I've
tried a few things suggested in other posts. E.g., inserting new columns
"Duration 1", then using using tools have gone to the customize fields window
and selected for summary tasks select Sum. The summary task then sums all of
the durations as calendar days. The problem is that some of the tasks are
concurrent. This gives me an inflated duration for the summary task. Any
ideas.
work days. The big problem is with "Summary Tasks". I can easily set
individual tasks to calendar days be specifying, for example, 5 edays
(elapsed days). But the summary task is still displaying work days. I've
tried a few things suggested in other posts. E.g., inserting new columns
"Duration 1", then using using tools have gone to the customize fields window
and selected for summary tasks select Sum. The summary task then sums all of
the durations as calendar days. The problem is that some of the tasks are
concurrent. This gives me an inflated duration for the summary task. Any
ideas.