Nic2024 said:
We have tasks that we're giving a set 80 hours to complete. This task will
be completed in 80 hours no matter how many people are working on this task
(which will fluctuate). Is there a setting that can make WORK = DURATION
despite how many resources are assigned?!
There has been so much written already in this newsgroup over the years
about work vs. duration. Suggest you go back and read some of the
classic posts.
Simply: Work is not duration and to make them the same makes no sense
to try to think of it that way. It's only coincidental that work 80
equals duration 80 (just numbers).
I think you are saying: The fixed duration, so tell Project it is a
Fixed Duration task, of this task is 80 hours. You have to decide if
this is 80 hours of work time, e.g. 8 ten hour days, or 10 eight hour
days, or 80 elapsed hours regardless of your work calendar. It is *not*
effort driven, so ensure effort driven is "no". Then when you assign
oodles (a technical term) of resources to that task, it will only take
the fixed duration that you told Project. Each resource should be given
only the number hours of work on the task so that when all assigned work
is summed, it add up to 80.
It's all in how you describe the Task.
Don't try to make work=duration because it never will be and you'll be
confused about Project as long as you try to make it so.